Snag lists and defect liability: closing a project without a tail of complaints

Room-by-room snagging, who fixes what, the defect liability period and the tracking that keeps a warranty claim from vanishing.

· PropERP· 3 min read

পড়ুন বাংলায়

A snagging inspection of interior finishes before handover

Handover is where three years of goodwill is either confirmed or spent. The mechanics are simple: inspect, rectify, offer possession, record what remains, and honour the defect liability period. Projects go wrong when the snag list lives in a notebook, rectification is tracked by whoever happens to remember, and the developer discovers six months later that thirty units still have open items nobody logged.

The sequence that works

  1. Internal pre-handover inspection by your own site team, room by room against a standard checklist.
  2. Rectification of everything found, before the buyer is invited.
  3. Joint inspection with the buyer, with the list signed by both.
  4. Rectification of buyer-identified items, with dated commitments per item.
  5. Handover — keys, meters, documents, warranty pack, signed handover certificate.
  6. Defect liability period runs, with a defined route for the buyer to report defects.
  7. Closure, and release of any retention held against the contractor. See certifying a contractor bill.

Step one is the one most often skipped and the one that determines the tone of everything after. A buyer whose first inspection finds three minor items behaves completely differently from one who finds forty.

A snagging checklist that catches what matters

Organise by room and by trade, so nothing depends on the inspector's memory:

AreaTypical items
Doors and windowsAlignment, locks, handles, seals, glass condition
Walls and ceilingsFinish, cracks, patching, paint coverage
FloorsLevel, tile lippage, grouting, skirting
ElectricalEvery socket and switch tested, DB labelled, earthing
PlumbingEvery tap and drain run, leaks, water pressure, flush operation
Kitchen and bathroomsFittings, sealant, cabinet operation, exhaust
Balcony and externalRailing fixing, drainage falls, waterproofing
Common areasLift operation, lobby finish, generator, water pump, fire equipment

Photograph each item at logging and again at rectification. A dated photograph pair ends nearly every dispute about whether something was fixed.

Tracking that survives the project

Each snag is a small record with the same fields: unit, location, description, photograph, responsible party, target date, status, and rectification photograph. The value is not in any single item; it is in the report — open items by unit, by trade and by age. That report tells you whether handover is on track and where the contractor is not performing, and it is the only reliable way to run a handover of a hundred units at once.

Aligning the two liability periods

The buyer has a defect liability period under the sale agreement. The contractor usually has one under the construction contract. If the contractor's expires first, the developer carries the tail alone. Align them at contract stage, and release contractor retention against the same record that closes buyer snags rather than against a separate conversation.

Handover as a sales asset

Buyers talk. A handover where the flat was clean, the list was short, and the open items were fixed on the dates promised produces referrals; the opposite produces a story that reaches every prospective buyer in the same social circle. Given how much a booking costs to acquire, the rectification budget is one of the cheapest marketing investments a developer makes. See what a delay costs for the same argument on timing.

What to do next

Take the last ten units you handed over and count the items still open, and how many days each has been open. If nobody can produce that number in five minutes, your defect liability exposure is unmeasured — see snags tracked per unit through to closure.

Frequently asked

Who should carry out the snagging inspection?
Ideally both sides — your team runs a pre-handover inspection and rectifies before offering possession, then the buyer inspects. A buyer who finds forty items on first sight assumes nobody looked.
How long is the defect liability period?
Whatever the agreement says, and it should say something specific. Where the contract with the main contractor also carries a defect liability period, the two should be aligned so the developer is not exposed after the contractor's obligation has expired.
What counts as a defect versus wear and tear?
Define it in the agreement with examples. Without a definition, every scratch becomes a negotiation, and the sales team ends up making promises during handover to keep the day pleasant.
Can we hand over with open snags?
Only with a signed list of what remains, dated commitments for each item, and the buyer's acknowledgement. An undocumented handover with open items is how a project acquires a reputation.

/solutions

Read next

All articles

Next step

See this working on your own project

Forty minutes, configured on one of your real projects. If the problem in this article is yours, that call is the fastest way to know whether it is solved here.

40 minutes · walked through on your project structure · no card required