Construction and procurement

Certifying a contractor bill: measurement, retention and running account

How a running account bill is built, what the site engineer must verify, and the deductions that belong on every certificate.

· PropERP· 3 min read

পড়ুন বাংলায়

A site engineer checking a contractor bill against work done

A contractor bill is not an invoice to be checked and paid. It is a claim about how much work has been completed, and certifying it means agreeing that claim against measurement. Get the certification chain right and payments are predictable, deductions are correct and disputes are rare. Get it wrong and you overpay early, then argue about it at the end when you have no leverage left.

The running account structure

LineBasisExample
Cumulative work doneMeasured quantities at contract ratesBDT 3,42,00,000
Less previously certifiedFrom the last billBDT 2,86,00,000
Certified this billDifferenceBDT 56,00,000
Less retentionContract percentage of certified valueBDT 2,80,000
Less advance recoveryPer the contract recovery scheduleBDT 5,00,000
Less source tax and VAT deductionStatutory, on the certified amountPer applicable rates
Net payableBalance

Two points about this structure. Deductions apply to the certified figure, not the claimed one — see AIT and VAT by transaction. And advance recovery has to follow the contract schedule; recovering "when we remember" is how a mobilisation advance survives to the end of the project.

What the site engineer must actually verify

  1. Quantity. Measured on site against the bill of quantities, not accepted from the contractor's sheet.
  2. Rate. Against the contract rate schedule, including any agreed rate for a variation.
  3. Quality gate. Work that has failed an inspection is not certified, regardless of quantity.
  4. Variation authority. Extra items require an approved variation order. An unapproved variation certified in a running bill is a change to the contract nobody agreed.
  5. Material supplied by the developer. Where you supply cement or steel, the value must be recovered, and that recovery depends on issue records — see site material control.

Retention, and remembering to release it

Retention protects you against defects, and it only works if the release conditions are recorded when the deduction is made. A retention register — contractor, project, amount held, release condition, release date — takes minutes to maintain and prevents both of the failure modes: releasing early because the contractor asked persistently, and holding money past the contract date, which damages the relationship and occasionally becomes a claim.

Retention release usually pairs with the defect liability period, which is also when snagging obligations bite — see snag lists and defect liability.

The same measurement feeds two things

The measurement that certifies a contractor bill is the same measurement that establishes construction progress for buyer milestone billing. Producing them from one record rather than two removes a whole class of inconsistency, where the site is 62 percent complete for the contractor and 55 percent for buyers. Milestone billing covers the buyer side.

Variations, the quiet budget killer

Most cost overruns on a building are not one large surprise. They are twenty variations, each individually reasonable, none of them re-costed against the budget at the time. A variation order should carry its own quantity, rate and value, and should update the forecast cost to complete when it is approved — not at the end of the project when the total is discovered.

What to do next

Take the last certified bill on your largest site and check four things: was the quantity measured or accepted, was retention applied at the contract rate, was advance recovered per schedule, and were deductions computed on the certified figure. Each "no" is money already gone — see certification, retention and deductions in one chain.

Frequently asked

What is a running account bill?
A cumulative bill. Each submission states the total work done to date at contract rates, and payment is the cumulative certified amount less everything already paid. It avoids arguments about which item was in which earlier bill.
How much retention should be held?
Five to ten percent of certified value is the usual band, released partly at completion and partly after the defect liability period. Whatever the figure, it must come from the contract rather than from practice.
Who is allowed to certify?
The site engineer or quantity surveyor named in the contract, on measurement. Certification by the person who negotiates with the contractor creates a conflict that eventually shows up in the numbers.
What if the contractor disputes the certified quantity?
Joint measurement, recorded and signed by both parties, before the bill is processed. A disputed quantity settled by conversation reappears in the next bill.

/solutions

Read next

All articles

Next step

See this working on your own project

Forty minutes, configured on one of your real projects. If the problem in this article is yours, that call is the fastest way to know whether it is solved here.

40 minutes · walked through on your project structure · no card required